Resource Report - Work Adjusted Calculation by % Complete

Follow

Comments

2 comments

  • Avatar
    Wes Kliewer

    The "Work Hours Remaining" is based upon the "earned value (hours)" versus the actual hours.

    Your suggestion is that the report would use another option, which is currently labeled in report columns as "Var. Work Hours vs Actual." That value can go into negative hours as time entries exceed the planned/estimated hours. For the purposes of the report, I presume that PI would value all work as 100% complete once the variance is 0 or fewer hours.

    0
    Comment actions Permalink
  • Avatar
    Rachel Wood

    Can this function so it calculates the remaining time by the actual hours inputted instead of the work status? And the work status would be auto-calculated based off of the actual hours instead of having to be set manually? Calculating the remaining time based on actual hours inputted instead of the work status is more accurate with how much time is remaining on the task. Is this possible to do?

    0